CLIENT: Thomas Armstrong (Aggregates) Ltd     VALUE: £3m     COMPLETION: August 2018     

DURATION: 26 weeks     CONTRACT: JCT D&B

WORKS INCLUDED

  • Ground investigation
  • Design
  • Procurement of specialist silo system
  • CFA piling
  • Reinforced concrete
  • Utility supplies
  • Cranage
  • Facility infrastructure

 

KEY RISKS/CHALLENGES

  • High loadings necessitating ground improvement
  • Harbour side location
  • Major cranage operation

 

LESSONS IMPLEMENTED

  • Weather watch to ensure safety of crane operations at a windy coastal site
  • Detailing of heavily reinforced bases simplified, implementing experience fromwind farm turbine bases
  • Silo storage chosen as an improvement on existing bulk cement storage facility

COLLABORATION AND VALUE ADDED

  • Early contractor involvement to optioneer piling to provide an economic groundimprovement / foundation solution
  • In-house ‘Appointed Person’ to scrutinise crane plans
  • Regional procurement policy  

 

PLANNING AND PROGRAMME

  • In-house ‘Appointed Person’ to scrutinise crane plans
  • Regional procurement policy  
  • Long lead on specialist equipment co-ordinated with site construction

SUCCESSFUL OUTCOMES

  • Exemplar Work at Height operations
  • Business development at the Port of Sunderland increasing trade
  • Additional cement supply option for regional precast manufacturing