CLIENT: Cumbria County Council     VALUE: £420,000     COMPLETION: August 2020     

DURATION: 10 weeks     CONTRACT: NEC 3 Option A

WORKS INCLUDED

  • Earthworks.
  • Drainage (with attenuation).
  • Lighting.
  • Vehicle access barriers.
  • Electric Vehicle Charge points.
  • Permeable block paving.
  • Bitumen macadam surfacing.
  • Road markings.

KEY RISKS/CHALLENGES

  • Poor ground conditions.
  • Access off Jubilee Road prone to congestion.
  • Site bordering open watercourse.
  • Office occupied during the Works.\

LESSONS IMPLEMENTED/COLLABORATION/VALUE ADDED

  • ‘Look Ahead’ liaison with Office users and office refurbishment contractors.
  • Early Contractor Involvement meeting with Cumbria Highways Local Area Network Team to agree access arrangements.
  • In-River working experience from the 2015 Floods’ Infrastructure Recovery Programme
  • Additional wind support to temporary fencing due to exposed location of the site

PLANNING AND PROGRAMME

  • Programmed to fit with ongoing refurbishment of the office building.
  • Access / egress planned to avoid travelling dirt onto the highway.
  • Banksman to marshal vehicle movements onto the highway.
  • Earthworks & drainage phased to protect sub-grade from the weather.
  • Contract correspondence managed to NEC 3 timescales with programme reviews & CE quotes agreed.

SUCCESSFUL OUTCOMES

  • Effective stakeholder management resulting in no complaints.
  • Tight contract timescale met.
  • Vehicle movements managed to keep highway clean during Groundworks operations.