St. Leonards A1 overpass - North Bound and South Bound dual carriageway.

CLIENT: Northumberland County Council    VALUE: £104,000     COMPLETION: October 2021      

DURATION: 9 days   CONTRACT: NEC 4

WORKS INCLUDED

  • Remove the failed subsurface drainage system
  • Waterproof the existing bridge deck
  • Plane out carriageway
  • Regulate with Asphaltic concrete
  • New expansion joints
  • Hot tanker Bond coat
  • HRA surfacing
  • Areas repaired with Polmer Modified Binder
  • Road markings
  • Contra flow traffic management

KEY RISKS/CHALLENGES

  • 24 hour working 7 days per week  
  • Major trunk road. It was imperative that we worked all available hours to achieve the programme and not delay the reopening of the dual carriageway in either direction
  • North bound dual carriageway carried out first followed by the South Bound dual carriageway
  • Some activities were weather dependent and could have delayed the contract with very little scope to mitigate overruns
  • Heavy traffic flows on a high-speed road

LESSONS IMPLEMENTED

  • Subcontractor liaison and planning was essential to the smooth running of the contract

COLLABORATION AND VALUE ADDED

  • Scheme administered through proven management system of our specialist Civil Engineering & Highways department.  

PLANNING AND PROGRAMME

  • Contract was completed on schedule

SUCCESSFUL OUTCOMES

  • No accidents
  • No pollution incidents
  • Works completed exactly on schedule