Phase 2

This scheme is on an extremely busy main arterial route into / out of Kendal and was completed, achieving the prime objective of minimising road-user inconvenience. Residents, businesses including B&Q, Asda and the local hospital, were all kept informed through implementation of our communication plan.

CLIENT: Cumbria County Council   VALUE: £360,000     COMPLETION: May 2018     

DURATION: 12 weeks    CONTRACT: NEC 3

WORKS INCLUDED

  • All aspects of Roadworks in a busy urban site
  • Statutory Authorities liaison to procure new electric supplies for street lighting upgrade

KEY RISKS/CHALLENGES

  • Early contractor involvement benefitted traffic management planning in advance of site work.  
  • Rush hour traffic.
  • Heavy pedestrian & cycle usage.  

LESSONS IMPLEMENTED

  • Early meeting with Local Area Network Team to agree approach to critical temporary traffic management design.  
  • Site based ‘point of contact’ for stakeholders.

COLLABORATION AND VALUE ADDED

  • Contractor local experience
  • Scheme administered through proven management system of our specialist Civil Engineering & Highways department.  
  • Embedded knowledge from previous Framework schemes & continuity of workload

PLANNING AND PROGRAMME

  • Planning informed by considerable site experience within Cumbria and local knowledge used to manage programme with proven established resource pool.  

SUCCESSFUL OUTCOMES

  • No accidents
  • No pollution incidents
  • No complaints (effective stakeholder management)