Public realm improvements to a popular underpass.

CLIENT: Allerdale Borough Council    VALUE: £223,000     COMPLETION: September 2021      

DURATION: 37 weeks    CONTRACT: NEC 3 Option A

WORKS INCLUDED

  • Road reconstruction and realignment
  • New streetlighting and ducts
  • Trieff kerbs
  • Block paving & kerbing
  • Erection of smoking shelters
  • Stonework jet cleaning with Dry Ice
  • Steel stanchion erection for future artwork murals
  • Tarmac surfacing and road markings
  • Sandstone walling

KEY RISKS/CHALLENGES

  • Minimising Road Closure duration  
  • Public information to reduce wasted vehicle journeys
  • children entering the site during non working hours

COLLABORATION AND VALUE ADDED

  • In-house surfacing gang on hand to complete the roadworks to re-open the highway

PLANNING AND PROGRAMME

  • Works completed on schedule