The replacement of the schools centralised heating and hot water generation plant and all distribution pipework and emitters within the school. Carried out over two summer holiday periods to suit the schools preferred schedule.

CLIENT: The School Governors     VALUE: £170,000     COMPLETION: September 2020 & September 2021   

DURATION: 6 + 6 weeks     CONTRACT: JCT 2016

MECHANCIAL WORK INCLUDED

  • Design
  • Gas fired boiler installation
  • LPHW Radiator heating system
  • Hot and cold water generation
  • Natural gas services

  • Thermal insulation
  • Automatic HVAC control system
  • Testing and commissioning
  • Handover documentation
  • First 12 months maintenance