The project involved the design, supply installation and commissioning of a new gas-fired boiler plant as well as replacement of the CHP plant within the existing boilerhouse whilst maintaining all heating and hot water provision throughout the duration of the works.

CLIENT: Eden District Council      VALUE: £230,000     COMPLETION: December 2017

DURATION: 9 weeks      CONTRACT: JCT Design & Build

WORKS INCLUDED

  • Design works
  • Temporary boiler hire
  • Phased strip out of the existing heating and CHP plant
  • Phased installation of new gas-fired boilers
  • Installation of new plate heat exchanger for domestic hot water production
  • New flue systems
  • New compartment ventilation

  • New pumps
  • Thermal insulation works
  • Automatic HVAC controls and wiring
  • Client training
  • Testing and commissioning
  • Handover documentation
  • First 12 months maintenance