No items found.
No items found.

CLIENT: Cumbria County Council     VALUE: £730,000     COMPLETION: September 2019     

DURATION: 52 weeks     CONTRACT: NEC 3 Option C

WORKS INCLUDED

Thomas Armstrong (Construciton) Ltd had to develop some initial designs that were put together by CCC, to full design and build status.

The two main packages were the stabilisation of a slope at Grisedale Lane near Patterdale using rock armour to prevent future erosion by the river and secure the integrity of the road above.

In the same area, at Hartsop, we undertook concrete underpinning to a stone wall within a river that had been undermined and washed out during the flooding, to prevent future wall and road collapse. Other works included road and drainage improvement works at Mungrisedale, Warcop and Bampton to Burnbanks.

The reprofiling of a riverbank at Warcop that had collapsed, including the installation of rock rolls and willow planting to stabilise the new slope.

KEY RISKS/CHALLENGES

  • Four of the schemes were undertaken within river areas consequently works had to be undertaken within the EA’s tight ‘in-river’ window of mid-July to the end of September
  • Ensuring that traffic flow for tourists was not adversely affected on the narrow road at Hartsop
  • Grisedale site was on a site that was heavily used by school parties on residential breaks. Careful consideration had to be given to ensuring the safety of these children who are not generally aware of the dangers of construction sites. It was also very close to a popular caravan site which relied heavily on repeat business, so disruption had to be kept to a minimum#
  • Installation of a temporary access route through a heavily wooded area and full restoration at completion at Grisedale Lane

LESSONS IMPLEMENTED

  • Thomas Armstrong (Construction) Ltd had to take over responsibility for negotiations with landowners to obtain agreements to access their land to ensure that works could be undertaken within the tight timescales.

COLLABORATION AND VALUE ADDED

  • Communication on a daily basis with site users to inform them on upcoming works, vehicle movements etc
  • Noise from our works was reduced by lining dumpers, transporting rock materials, with sound deadening quilts

SUCCESSFUL OUTCOMES

  • Minimal disruption to site users, traffic and local residents & business’s
  • Minimal disruption to local traffic flow

To view the work carried out as part of the Grisdale Beck Slope Project, click here.

Download PDF