This project involved the construction of 34 No. new timber frame lodges, consisting of 14 No. two-bed executive lodges, 7 No. three-bed executive lodges, 12 No. three-bed executive lodges offering a hot tub experience and 1 No. six-bed single storey lodge.  

Also included was the demolition of the existing arrivals lodge to make way for 120 additional parking spaces, adjacent the existing main car park and a new 10 bay arrivals lodge building which is to be erected as part of the scheme located to the north east of the main car park.

CLIENT: Center Parcs, Penrith     VALUE: £7m (Mechanical - £770,000)  COMPLETION: April 2019    

DURATION: 60 weeks     CONTRACT: JCT Intermediate

BUILIDING - CHALLENGES AND HOW THEY WERE OVERCOME

The interface with the 5,000 to 6,000 guests who occupy the park at any one time was paramount.  Regular meetings were held with the park’s management team.  Delivery of materials had to be timed to avoid Mondays and Fridays, which are the busiest days on the park.  There were numerous work phases ongoing at the same time which needed additional site supervision, which we provided.

ACHIEVEMENTS

  • The project was delivered on programme.
  • The project was delivered with zero reportable Health & Safety incidents.
  • The project was delivered with zero environmental notices issued.
  • 76% of subcontractors used were local to the project site.
  • High level of customer satisfaction, resulting in repeated tender opportunities.

MECHANICAL WORKS INCLUDED

  • External gas and water infrastructure
  • Gas boiler installations, radiator heating and controls
  • Hot and cold water services
  • Ventilation
  • Above ground drainage and sanitary ware