Groundworks for New Aldi Store

Groundworks package including Section 56 works and construction of SW outfall into the river.

CLIENT: Aldi Bathgate Region     VALUE: £1.5m     COMPLETION: November 2021      

DURATION: 35 weeks    CONTRACT: JCT 2016

WORKS INCLUDED

  • Bulk Excavations, dealing with contamination
  • Foundations, retaining walls and floor slabs.
  • SuDS drainage and attenuation
  • Junction realignment works and constructing new entrance.
  • Surfacing (carriageway & footway)

KEY RISKS/CHALLENGES

  • Occupied Commercial properties required access through the site, including an Ambulance Station.
  • Works to the new junction to be co-ordinated around the school break times.

LESSONS IMPLEMENTED, COLLABORATION AND VALUE ADDED

  • TAC vast experience led to the successful re-design of the SW outfall to mitigate unforeseen site conditions.
  • Liaison with ambulance station confirming their access route.
  • Planning & programme
  • Liaison with Ayrshire Road Alliance.
  • In-house gangs and equipment, eliminating need to co-ordinate sub-contractors

SUCCESSFUL OUTCOMES

  • School access safeguarded
  • Roadworks adopted by Ayrshire Highways
  • Store opened on planned date to meet the Xmas trade